£23m landslip repair set to reopen Settle-Carlisle railway line in March 2017

Published on : Friday, July 8, 2016

9-300x255Repairs to a 500,000-tonne landslip in Cumbria will see the iconic Settle to Carlisle railway line fully reopen to trains by the end of March 2017, Network Rail announced today.Engineers are building an enormous concrete and steel, tunnel-like structure that will sit beneath the railway, 70 metres above the River Eden, to provide a stable base across the damaged and unstable ground.

 
Two rows of high-strength piles – steel tubes filled with concrete – will then be driven into the sloping bedrock of the Eden gorge, north of Armathwaite.The hundreds of piles will form a corridor, set into the hillside, on which a 1.5 metre-thick, 100 metre-long concrete slab will then be placed. This slab will form a solid base for the tracks.

 
This £23 million engineering solution was selected by Network Rail from among six* possible options.This structure will stabilise a section of gorge bank above the River Eden which gave way in February causing ground below the railway to slip 1.5 metres below its normal level in the weeks that followed.

 
Since then the line has been shut, initially between Appleby and Carlisle, until Northern services began running as far as Armathwaite in June, with buses operating between Armathwaite and Carlisle.

 
In addition to the solid structure being built beneath the railway, an extensive earthworks project, costing an estimated £5 million, is planned to protect the foot of the bank down to the river. Drainage systems and ‘rock armour’, which helps prevent erosion, followed by tree replanting will stabilise the land.

 
Martin Frobisher, managing director for Network Rail’s London North Western route, said: “The tunnel-like structure we’re building will safeguard this section of railway for generations to come. If the land gives way again, the railway will not.

 

“This is a complex repair job many months in the planning. We are now focused on getting this iconic and much-loved line fully reopened right the way to Carlisle as soon as possible, which according to our programme of work will be by the end of March 2017.

 
“We recognise the impact the closure of the line between Appleby and Carlisle has had on local communities, especially during the summer tourist season, and we’re really pleased Northern now have services running as far as Armathwaite. We would remind people that the Settle-Carlisle Line remains very much open for business.

 

“Network Rail remains strongly committed to the Settle-Carlisle line. We regard this line as an essential freight corridor and vital for local communities and the regional economy.”

 
Today Network Rail teamed up with members of the Friends of Settle Carlisle Line (FoSCL) and Northern to meet with local people, calling at homes and dropping leaflets in the local communities of Appleby, Langwathby, Lazonby, Kirkoswald and Armathwaite.

 

 
Between 3pm and 7pm on Thursday 7 July a public drop-in session will be held for local residents at the village hall in Armwathwaite. Members of the project team will be on hand to answer questions.

 
While the Appleby-Carlisle section of the line has been shut Network Rail has carried out other upgrades to avoid additional future disruption, including embankment strengthening at Barons Wood and improvements to Low Mill level crossing.

 

Source:-Network Rail

Comments are closed.

arrow2Follow Us
 
facebook-logo  twitter-logo  LinkedIn_logo  stumbleupon-logo   rss_logo 

SUBSCRIBE NEWSLETTER:

Email 
 

ADVERTISEMENT

    TRAVEL INDUSTRY EVENTS

    More Events...