Major weekend of progress at Dover sea wall marred by rock-throwing youths

Published on : Wednesday, June 22, 2016

310(3)A major milestone has been achieved by the project to rebuild the railway at Dover, despite the actions of a group of youths throwing rocks at workers.One of the rocks, thrown from the cliff overnight last night  narrowly missed a staff member. Rocks had previously been thrown on Friday night.

Dover and Deal MP Charlie Elphicke has condemned their actions, saying: “The rocks missed site workers by inches and if they hit anyone, they could have been killed or at the very least have been seriously injured.

“I appeal to anyone who may know who these yobs are to come forward and to parents to talk to their children about the dangers of this kind of behaviour.“All this has distracted from the incredible progress made by Network Rail and their partners Costain in building the first section of the viaduct here at the Dover sea wall. I’ve been massively impressed by the hard work and dedication of the team, who worked tirelessly to rebuild our railway and we need to support them in any way we can and do our bit to help keep them safe.”

Network Rail’s programme manager Steve Kilby said: “The consequences of a serious injury or fatality as a result of someone being hit by one of these stones would be enormous. We are taking action to put our own 24/7 security and lighting at the top of the cliff.”

More than 500 cubic metres of concrete was poured into place over the weekend, in a 15 hour continuous operation involving a fleet of 13 concrete vehicles from Kent supplier Brett concrete, using their plants at Dover and Ramsgate.

That’s almost enough concrete to fill Dover Leisure Centre’s swimming pool twice over.Steve Kilby added: “This was a serious feat of organisation and we knew that once we started to pour the concrete, we couldn’t stop until the whole pour was completed. That way we knew the deck would be one consistent slab with no joins.

“I’d like to pay tribute to our contractor Costain and concrete supplier Brett Concrete for their work this weekend. We’ve now got to do it three more times before the viaduct structure is complete!”

The concrete pouring started at 8pm on Saturday and finished soon after 11am on Sunday.Chris Chapman, managing director of Brett Concrete, said: “This was a challenging pour and our plants and drivers worked around the clock to deliver a quality product at the right time. We have had a great working relationship with both Costain and Network Rail since the planning started on these pours three months ago.”

The railway along the beach at Dover has been closed since Christmas 2015. Network Rail is creating a new, 235m long viaduct that will sit on 134 piles – steel and concrete columns – of which more than 100 have been completed so far.

Source:-Network Rail

Comments are closed.

arrow2Follow Us
 
facebook-logo  twitter-logo  LinkedIn_logo  stumbleupon-logo   rss_logo 

SUBSCRIBE NEWSLETTER:

Email 
 

ADVERTISEMENT

    TRAVEL INDUSTRY EVENTS

    More Events...